Bill of quantities (BoQ) in the Philippines

A Bill of Quantities (BoQ) in the Philippines is an itemised schedule of work that breaks down a construction project trade by trade—earthworks, concrete, rebar, masonry, roofing, architectural finishes, electrical, and plumbing. Each line item specifies the measured quantity, unit of measurement, and unit price analysis combining materials, crew labour, equipment, markups, and taxes. Countstruct generates a complete BoQ directly from your floor plan and room schedules with presets for owners, contractors, and DPWH standards.

Basahin sa Filipino

How to estimate it

  1. Set up room schedules and geometry

    Each room is entered once: its name and level (floor), its length and width (or floor area and wall length when not a rectangle), ceiling height, doors and windows, and its finishes (floor, walls with paint or tile height, ceiling boards and paint, and optional light points and outlets). Updating finishes from rooms turns them into ordinary calculator estimates, where rooms on the same level that share a finish make one estimate.

  2. Divide into construction trade divisions

    A Philippine house BoQ is grouped into standard trade divisions:

    • Earthworks: Structural excavation, gravel bedding, backfill, and surplus soil hauling.
    • Concrete & Formwork: Footings, tie beams, columns, beams, suspended slabs, stairs, and slabs on fill.
    • Reinforcing Steel: Deformed bars (10 mm to 25 mm), lap splices, and #16 GI tie wire.
    • Masonry: 4", 6", or 8" CHB walls, mortar for laying, and two-face cement plastering.
    • Roofing & Tinsmithry: Steel trusses, C-purlins, corrugated or long-span sheets, tek screws, and ridge rolls.
    • Architectural Finishes: Ceiling framing and boards, floor and wall tiles, paint, doors, and windows.
    • Electrical & Plumbing: Rough-in conduits, THHN wiring, panel boards, sanitary drainage, and water lines.
  3. Build the Detailed Unit Price Analysis (DUPA)

    Each item's cost is structured into direct costs, markups, and taxes:

    • Direct Cost: Materials + Crew Labour (foreman, skilled workers, helpers) + Minor Tools (percentage of labour) + Equipment rentals.
    • Markups: Direct Cost × (Contingency % + Overhead/OCM % + Profit %).
    • Value Added Tax (VAT): (Direct Cost + Markups) × VAT %.
  4. Apply budget presets

    Countstruct provides three standard Philippine budgeting presets:

    • Owner: 0% minor tools, 10% contingency, 0% overhead, 0% profit, 0% VAT. Direct materials and labour with a safety reserve.
    • Contractor: 10% minor tools, 5% contingency, 10% overhead (OCM), 10% profit, 12% VAT.
    • DPWH Standard: 10% minor tools, 0% separate contingency (included in OCM), 8% to 15% OCM, 8% to 10% profit, 5% tax.
  5. Include general requirements

    Account for job-site overheads: one-time lump sums (mobilization, temporary bodega/facilities, permits, safety and health, signboard, clean-up) and monthly expenses (site engineer supervision, watchman, temporary water and power).

Worked example

A Bill of Quantities organizes measured scope into clear trades, work descriptions, and commercial quantities before pricing is applied:

Sample quantities for a small house, for illustration only
Trade Division Work Item Description Quantity Unit
Masonry Concrete hollow blocks (CHB) 4-inch 394 pcs
Masonry Portland cement (mortar & plaster) 28 bags
Masonry Washed sand 2.5 m³
Concrete Class A concrete (footings, columns, beams) 12.0 m³
Concrete Class B concrete (slab on fill) 2.1 m³
Rebar Deformed bar 16 mm × 6 m (columns & beams) 16 pcs
Rebar Deformed bar 10 mm × 6 m (ties & slab) 36 pcs
Rebar #16 GI tie wire 10 kg
Roofing Long-span rib-type roofing, 0.4 mm 45 m
Roofing C-purlin 2"×4" × 1.5 mm, 6 m 18 pcs
Roofing Tek screws 2½" with rubber washer 315 pcs
Finishes Ceramic floor tiles 60 × 60 cm 10 boxes
Finishes Acrylic latex paint (flat & semi-gloss) 6 gallons
Electrical Building wire 2 boxes
Electrical PVC electrical conduit ½", 3 m 24 lengths
Plumbing Water pipe ½", 4 m 8 lengths
Plumbing PVC sanitary drain pipe 4", 3 m 6 lengths

The app prices the result from its regional price book.

What the Countstruct calculator adds

Countstruct Bill of Quantities Features

  • Consolidates results from 51 individual material calculators into a unified project bill of quantities.
  • Integrated Room Schedule: enter rooms and dimensions once to generate floor finishes, wall paint, and ceiling boards.
  • One-click toggling between Owner, Contractor, and DPWH budgeting presets.
  • Pre-loaded regional daily labour wage rates for all 18 Philippine administrative regions.
  • Instant export to professional client PDF quotations, Excel, plain text and Google Sheets.
Create a Bill of Quantities in Countstruct

Questions

What is the difference between a material takeoff and a BoQ?

A material takeoff only produces a shopping list of physical supplies to purchase from a hardware store. A Bill of Quantities (BoQ) is a contractual document that itemizes work by construction division, integrating crew labour costs, equipment rentals, contractor markups, and VAT.

What does OCM stand for in Philippine construction bids?

OCM stands for Overhead, Contingencies, and Miscellaneous expenses. It covers off-site office management, insurance, financing, bidding costs, and unforeseen construction conditions.

How does Countstruct's Room Schedule work?

You input room dimensions (length, width, ceiling height) and door/window openings once. The system automatically computes net wall paint areas, floor tile boxes, adhesive, and ceiling framing, updating all project lines simultaneously.

Why is VAT different between private and DPWH projects?

The DPWH preset uses 5% (DO 197 s.2016); 12% is the statutory rate and the contractor preset's figure; some agencies use 12%, so change it if yours does.