Rebar calculator for columns, beams and slabs
Reinforcing steel bars in the Philippines are sold in standard commercial lengths of 6 metres, with diameters from 10 mm to 25 mm. To estimate rebar accurately, you must calculate the cut length of each bar including lap splices (typically 40 bar diameters) and 135° hooks (NSCP 2015 Sec. 425.3), determine how many pieces can be cut from each 6 m stock bar without reusing offcuts, and calculate #16 GI tie wire at 0.30 m per crossing (53 m per kg).
Calculator
Estimate column main bars and ties cut from 6 m stock. Open the column rebar calculator in Countstruct.
How to estimate it
-
Calculate main longitudinal or vertical bars
For columns and walls, each bar cut length equals the clear height plus the lap splice extending into the floor above (standard 40 bar diameters, 40d). For beams, bar length equals the clear span plus 90-degree development hooks into the column joints (2 × 12d):
Cut Length = Height (or Span) + Lap Splice (40d) -
Determine cuts from 6 m commercial stock bars
Determine how many full pieces can be cut from a single 6-metre stock bar. Offcuts are discarded as scrap and not reused:
Pieces per Bar = ⌊6 m ÷ Cut Length⌋Stock Bars = ⌈Total Pieces ÷ Pieces per Bar⌉For spans or heights longer than 6 m, splices are calculated using
Splices = ⌈(Length − 6) ÷ (6 − Lap)⌉. -
Calculate lateral ties and beam stirrups (10 mm)
Ties and stirrups prevent bar buckling and resist shear stresses. They are spaced at 0.10 m, 0.15 m, or 0.20 m along the height or span:
Ties per Member = ⌊Height ÷ Spacing⌋ + 1Girth accounts for concrete cover (40 mm on each side) plus two 135° hooks (NSCP 2015 Sec. 425.3) (0.105 m each for a 10 mm tie):
Tie Girth = 2 × (Width − 0.08) + 2 × (Depth − 0.08) + 2 × 0.105 mStock 10 mm Bars = ⌈Total Ties ÷ ⌊6 m ÷ Tie Girth⌋⌉ -
Calculate #16 GI tie wire in kilograms
Count every point where a main bar crosses a tie or stirrup. Wire is cut at 0.30 m per tie for bars up to 12 mm (0.40 m for 16 mm and larger). Commercial #16 tie wire yields approximately 53 metres per kilogram:
Tie Wire (kg) = (Crossing Points × 0.30 m) ÷ 53 m/kg
Worked example
Consider 4 columns, 0.25 × 0.25 m in cross-section, 3 m high, each reinforced with 4 main bars of 16 mm diameter, and 10 mm lateral ties spaced at 0.15 m with a 40d lap splice:
| Component | Formula / Cutting Logic | Quantity to Order |
|---|---|---|
| Main Bar Cut Length | 3.0 m + (40 × 0.016 m) = 3.64 m | 3.64 m each |
| Main Bar Pieces | 4 columns × 4 bars = 16 pieces | 16 pieces |
| 16 mm × 6 m Stock Bars | ⌊6 ÷ 3.64⌋ = 1 piece per 6 m bar 16 pieces ÷ 1 piece/bar |
16 bars of 16 mm × 6 m |
| Ties per Column | ⌊3 ÷ 0.15⌋ + 1 = 21 ties | 21 ties / col |
| Total Ties (4 columns) | 4 columns × 21 ties = 84 ties | 84 ties |
| Tie Girth | 2 × 0.17 + 2 × 0.17 + 2 × 0.105 = 0.89 m | 0.89 m each |
| 10 mm × 6 m Stock Bars | ⌊6 ÷ 0.89⌋ = 6 ties per 6 m bar ⌈84 ÷ 6⌉ = 14 bars |
14 bars of 10 mm × 6 m |
Offcuts are not reused. The app prices the result from its regional price book.
What the Countstruct calculator adds
Countstruct Rebar Calculator Features
- Calculators for columns, beams, tie beams, isolated footings, wall footings, slabs, and stairs.
- Commercial 6 m stock bar cutting rules without impractical scrap reuse assumptions.
- 135° hooks (NSCP 2015 Sec. 425.3) and laps of 40, 50 or 60 bar diameters (40d by default).
- Precise concrete cover subtractions: 75 mm against soil, 40 mm for beams/columns, and 20 mm for suspended slabs.
- Automatic #16 GI tie wire calculation.
Questions
Why are rebar orders based on 6-metre stock bars?
In retail Philippine hardware stores, deformed steel bars are stocked, transported, and sold in 6.0-metre lengths. While mills produce 7.5 m, 9 m, and 12 m bars for high-rise projects, residential and small commercial construction relies on 6 m bars.
What does a 40d lap splice mean?
40d means the overlap length is 40 times the bar diameter: 0.40 m for a 10 mm bar, or 0.64 m for a 16 mm bar. The lap is an estimating rule of thumb; ACI 318-14 Class B laps work out to about 37d for Grade 40 (Grade 275) bars and 57d for Grade 60 (Grade 420) in 21 MPa concrete. Always follow the lap on your structural plans.
How many metres of #16 tie wire are in one kilogram?
Standard #16 galvanized iron (GI) wire yields approximately 53 metres per kilogram in estimating practice, which includes allowances for wire twists, trimming, and site waste.
Why are offcuts not reused in the calculation?
The app counts whole cuts from each 6 m bar and does not count offcuts, so the order is never short; reusing offcuts on site lowers the real need.