Concrete calculator: bags of cement per cubic meter

One cubic metre of concrete takes 9 bags of 40 kg cement for Class A (1:2:4), 12 bags for Class AA (1:1.5:3), 7.5 bags for Class B (1:2.5:5) and 6 bags for Class C (1:3:6). Every class also takes 0.5 m³ of sand and 1.0 m³ of gravel per cubic metre. Add 5% for waste: a 5 m × 4 m slab, 10 cm thick, in Class B needs 16 bags of cement, 1.5 m³ of sand and 2.5 m³ of gravel.

Quick answers

Question Answer
Bags of cement per m³, Class A (1:2:4) 9 bags of 40 kg
Bags of cement per m³, Class AA, B and C 12 (AA), 7.5 (B), 6 (C)
Sand and gravel per m³ of concrete 0.5 m³ sand and 1.0 m³ gravel, every class
Cement per m² of a 10 cm (4") slab 0.75 bag in Class B; 0.9 bag in Class A, before waste
Concrete from one 40 kg bag, Class A About 0.11 m³ (1 ÷ 9)
5 m × 4 m × 10 cm slab, Class B, 5% waste 16 bags, 1.5 m³ sand, 2.5 m³ gravel

Factors are Fajardo Table 1-2 for volumetric site mixes with 40 kg bags. Sand and gravel are rounded up to the half m³, the way they are ordered.

Calculator

Estimate concrete volume, cement, sand and gravel for your slab. Open the concrete calculator in Countstruct.

How to estimate it

  1. Calculate structural concrete volume

    Multiply length by width by thickness (in metres). The app offers 0, 5 or 10% waste, with 5% as the default:

    Volume = Length × Width × Thickness × (1 + waste)

  2. Choose the concrete mix class

    Philippine builders use volumetric site-mix classes following standard estimating practice (Fajardo Table 1-2). Each cubic metre requires 40 kg cement bags, sand, and gravel as shown:

    Class Proportion (Cement : Sand : Gravel) 40 kg Cement Bags Sand (m³) Gravel (m³) Typical Application
    Class AA 1 : 1.5 : 3 12.0 0.5 1.0 Underwater, precast, high-strength
    Class A 1 : 2 : 4 9.0 0.5 1.0 Beams, columns, footings, suspended slabs
    Class B 1 : 2.5 : 5 7.5 0.5 1.0 Slabs on fill, pavements, ground floors
    Class C 1 : 3 : 6 6.0 0.5 1.0 Plant boxes, lean concrete, blinding beds
  3. Calculate cement, sand and gravel

    Multiply the net concrete volume by the mix factors. Cement is rounded up to the whole bag. Sand and gravel are rounded up to the nearest 0.5 m³:

    Cement = ⌈Volume × Bags per m³⌉

    Sand = Volume × 0.5 m³ (rounded to 0.5 m³)

    Gravel = Volume × 1.0 m³ (rounded to 0.5 m³)

  4. Include companion materials

    Ground-supported slabs require a compacted gravel bed (typically 0.05 to 0.10 m thick). Slabs also require reinforcing deformed bars (10 mm or 12 mm spaced both ways), #16 GI tie wire, and edge or soffit formwork.

Worked example

Consider a ground-floor slab on fill measuring 5 m × 4 m × 0.10 m, poured with a Class B mix, and a 5% waste allowance:

Material Formula / Calculation Quantity to Order
Concrete Volume 5 m × 4 m × 0.10 m × 1.05 waste 2.1 m³
Portland Cement (40 kg) 2.1 m³ × 7.5 bags/m³ = 15.75 bags 16 bags
Washed Sand 2.1 m³ × 0.5 m³/m³ = 1.05 m³ 1.5 m³
Crushed Gravel 2.1 m³ × 1.0 m³/m³ = 2.1 m³ 2.5 m³

Sand and gravel are bought by the half m³ (1.05 m³ rounds up to 1.5 m³, and 2.1 m³ rounds up to 2.5 m³). The app prices the result from its regional price book.

Back to the calculator ↑

What the Countstruct calculator adds

Countstruct Concrete Calculator Features

  • Full support for Class AA, Class A, Class B, and Class C concrete mixes with 40 kg cement bags.
  • Distinction between slabs on fill (with free edge forms and gravel bedding) and suspended slabs (with full soffit plywood and shoring).
  • Rebar grid scheduling for 10 mm and 12 mm bars spaced both ways with laps, covers (40 mm on fill, 20 mm suspended), and #16 GI tie wire.
  • Formwork plywood sheets, coco lumber framing (board feet), and common wire nails, factoring in realistic 3-use reuse cycles.
Open the concrete slab calculator in Countstruct

Questions

What is the difference between Class A and Class B concrete?

Class A (1:2:4, 9 bags of cement per m³) is standard for major load-bearing structural elements such as columns, beams, suspended second-floor slabs, and footings. Class B (1:2.5:5, 7.5 bags per m³) is used for ground-supported slabs on fill and pavements.

Why do all concrete classes use 0.5 m³ sand and 1.0 m³ gravel?

In volumetric batching (Fajardo Table 1-2), 1.0 m³ of gravel provides the solid skeleton of aggregate, while 0.5 m³ of fine sand fills the voids between the stones. The cement paste fills the microscopic gaps and bonds the aggregate together.

How thick should a residential concrete floor slab be?

The app's default for a slab on fill is 0.10 m with a 0.10 m gravel bed and 10 mm bars at 0.40 m both ways. Thickness and reinforcing must follow the plans.

How are sand and gravel ordered in the Philippines?

Sand and gravel are ordered by the m³; the app rounds up to the half m³.

How many bags of cement in 1 cubic meter of concrete?

9 bags of 40 kg for Class A (1:2:4), 12 for Class AA, 7.5 for Class B and 6 for Class C.

How many bags of cement for a 4-inch slab per square meter?

A 10 cm slab holds 0.10 m³ per m², so Class B takes 0.75 bag per m² and Class A 0.9 bag per m², plus 5% for waste.